By Segun James
Lagos State Governor, Mr. Babajide Sanwo-Olu has disclosed that a 32-metric ton per hour rice mill being constructed in Imota, Ikorodu division will start operations before end of first quarter in 2022.
Sanwo-Olu explained that the project could have been delivered at the end of 2020, though the outbreak of Coronavirus (COVID-19) disrupted the proposed date of delivery.
He gave the new date of delivery during the inspection of the project alongside the Commissioner for Agriculture, Ms. Abisola Olusanya and other members of the state executive council.
During the inspection, Sanwo-Olu said the facility would be subjected to a pre-production test run before the end of first quarter next year, after which the full production capacity would be activated rice production.
Sanwo-Olu said he was elated at the level of progress achieved on the project, having met the project from the foundation level.
He said the project could have been delivered at the end of 2020, but for the disruption occasioned by the outbreak of Coronavirus (COVID-19).
He said the new deadline remained sacrosanct, promising to prevail on all contractors working at the site to ramp up their activities before the next year first quarter.
Sanwo-Olu said: “I am happy with what I am seeing on the site and we are working to meet the deadline for the pre-production test run.
“We are going to charge on our contractors working on site to ensure that by the end of the first quarter next year, this mill should have started operations; that is, we should start producing rice from here.
“What is left is to see how quickly we can ramp up work on the storage facility, which has the capacity to take production up to three to six months.
“There are 16 silos, which have combined capacity of 40,000 metric tons. Each has 2,500 metric tons. The two sections of the silos are at about 85 and 70 per cent completion.”
Sanwo-Olu said construction work on the storage facilities would be completed in the next four weeks, after which major cleanup would commence across the major site in preparation for production test run.
When delivered, he said discussion around operation mode and production process would begin. He said full production of the facility would drastically reduce prices of rice and pressure to purchase the commodity.
“We are very much excited with how far we have gone on the construction. We are believing that all the contractors are working collaboratively to ensure the deadlines set are met,” the governor said.
The rice mill has been built with a capacity to produce 2.8 million bags of 50kg bags of rice yearly, while generating 1,500 direct jobs and 254,000 indirect jobs.
The State Government is also developing an industrial park adjacent to the mill. The Governor said the park would have amenities that would make businesses thrive and bring returns on investment to business owners. (THISDAY)

122603 195568Hello. Neat post. There is an issue together with your internet site in firefox, and you might want to test this The browser could be the market chief and a big part of other folks will miss your wonderful writing because of this difficulty. 236026
943622 872931Just wanna remark on few general points, The web site style is ideal, the topic matter is rattling good 184429
896990 698410Amazing beat ! I would like to apprentice whilst you amend your internet website, how can i subscribe for a weblog internet site? The account helped me a applicable deal. I had been tiny bit acquainted of this your broadcast provided shiny transparent concept. 417858